Digital Engineering

View Original

Final Phase of Terry Parkway Drainage Improvements Project Underway

As the design engineer for drainage improvements to Terry Parkway, we are excited to see the final phase of this project in motion. Due to budgetary constraints this $17 million project has been constructed in four phases with the final phase featured in the article below.

DE has provided hydraulic analysis, design, plan preparation, bidding, construction administration, and resident inspection services for the installation of over 3,000 lf of a double cell concrete box culvert and concrete flume to enclose an existing drainage canal along Terry Parkway from Carol Sue Avenue to Industry Canal. Other improvements include the restoration of existing concrete streets, installation of landscaping, installation of street lighting, and other utility relocations (water and sewer) to facilitate the box culvert construction.